Posted by lvpaul on 01/26/06 11:36
Hi Hugo !
Thanks - it works fine.
INSERT INTO POOL_LIEFERDAT(aufnr,werk,lstueck,ldatum)
SELECT a.aufnr,a.werk,a.voffenstueck -
coalesce(sum(l.lstueck),0),'31.12.2006'
FROM FAKT_AUFTRAG a
LEFT OUTER JOIN POOL_LIEFERDAT l
ON a.aufnr = l.aufnr and a.werk = l.werk
GROUP BY a.aufnr,a.werk,a.voffenstueck
HAVING a.voffenstueck > coalesce(sum(l.lstueck),0)
At the moment I am writing one record with the difference.
But in the future I want to write each time 4 records with
Record1: pieces = coalesce(sum(l.lstueck),0)/4, date = dateXY
Record2: pieces = coalesce(sum(l.lstueck),0)/4, date = dateXY + 1
months
Record3: pieces = coalesce(sum(l.lstueck),0)/4, date = dateXY + 2
months
Record4: pieces = coalesce(sum(l.lstueck),0),/4 date = dateXY + 3
months
I want to distribute the virtual call offs over the next 4 month !
Is it possible to make this with SQL ??
Paul
Navigation:
[Reply to this message]
|